TyreeSerini163 TyreeSerini163
  • 23-03-2014
  • Mathematics
Answered

Six people to can perform a task in 8 days. If we add 2 equally able people, how long would it take?

Answer :

madankapoor10
madankapoor10 madankapoor10
  • 23-03-2014
1 man does 1/48th piece of work per day
then 8 man do 1/6th piece of work per day
so they can do the work in 6 days

Answer Link
salmheiri
salmheiri salmheiri
  • 21-02-2022

Answer:

6 days

Step-by-step explanation:

Answer Link

Other Questions

Read this sentence Janna needed to complete all of her homework before she would be allowed to go to the football game so she went to the library right after sc
Solve for x 74x13x
Which sign makes the statement true89 8 68100
Consider The Equation 6x 3y 12 What Is The Slope Graph Of This Equation
What opinion about love does the speaker in Sonnet 29 When in disgrace with fortune and mens eyes express A Love is easier to find if one is wealthy B People in
Describe how the development of a special beak shape could affect a bird species survival
7 inches and 231 inches what is the scale factor for the set
sean has a piece of string 78 meter long he uses 15 of the piece of string to tie a package and cuts the rest into 5 equal pieces what is the length of each pie
Life for the average ancient Egyptian was carefree and easy A YES B NO
Three common characteristics of huntergatherer societies were